Project Duration
Stipulated Date of Commencement
October 18 2020
Stipulated Date of Completion /
Likely Date of Completion October 17 2023
Likely Date of Completion October 17 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,206,200.00
Awarded for
₹ 1,411,200.00
Project highlights
Maintenance Work
Contractors
M/s. Super Cool Refrigeration Industries
Consultants
In-house (GSIDC)