Project Duration
Stipulated Date of Commencement
December 19 2009
Stipulated Date of Completion /
Likely Date of Completion August 18 2010
Likely Date of Completion August 18 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 37,738,817.00
Awarded for
₹ 37,340,650.00
Contractors
M/s. Vigneshwar Air Conditioning Pvt. Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.