Project Duration
Stipulated Date of Commencement
May 05 2008
Stipulated Date of Completion /
Likely Date of Completion October 01 2008
Likely Date of Completion October 01 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,070,000.00
Awarded for
₹ 3,222,000.00
Contractors
M/s. ThyssenKrupp Elevator (India) Pvt. Ltd.
Consultants
M/s. Architecture Autonomous / M/s. Mahimtura Consultants Pvt. Ltd.