Project Duration
Stipulated Date of Commencement
March 26 2007
Stipulated Date of Completion /
Likely Date of Completion July 25 2007
Likely Date of Completion July 25 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,534,853.00
Awarded for
₹ 2,484,551.20
Contractors
M/s. A Square Techno Solution
Consultants
M/s. Effective Architectural Services