Project Duration
Stipulated Date of Commencement
July 17 2013
Stipulated Date of Completion /
Likely Date of Completion October 16 2013
Likely Date of Completion October 16 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,668,531.00
Awarded for
₹ 6,488,131.00
Contractors
M/s. Shree Manguirish Air Conditioning Company
Consultants
M/s. Gurudutt Sanzgiri