Project Duration
Stipulated Date of Commencement
November 15 2005
Stipulated Date of Completion /
Likely Date of Completion December 15 2005
Likely Date of Completion December 15 2005
Status
100%
Completed
Cost (₹)
Estimated at
₹ 611,117.00
Awarded for
₹ 641,000.00
Project highlights
The laying of paver blocks was taken up on the balance portion of the promenade on the riverside from Patto bridge to Miramar circle.
Contractors
M/s. D. K. Bhomkar
Consultants
M/s. Prabhugaonker & Associates