Project Duration
Stipulated Date of Commencement
October 01 2017
Stipulated Date of Completion /
Likely Date of Completion November 30 2017
Likely Date of Completion November 30 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,999,277.00
Awarded for
₹ 1,963,600.00
Project highlights
Interior Furniture Works
Contractors
M/s.Creation Interior Contractor
Consultants
M/s. Rahul Deshpande & Associates