Project Duration
Stipulated Date of Commencement July 26 2016
Stipulated Date of Completion /
Likely Date of Completion
September 08 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 999,534.00
Awarded for ₹ 1,044,450.00

Project highlights

The scope of work includes supply, installation, testing & commissioning of :
a) 160kVA,11/.415kV Distribution transformer
b) 11kV Load Break Switch
c) HT Metering cubicle and other allied electrical works.

 
Gallery Image
Contractors
M/s. Aditya Electromech Services
Gallery Image
Consultants
M/s. Archivista Engineering Projects. Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Construction of new building & repairs for existing building for Govt. Higher Secondary School at Canacona.

View Project
Similar Project

Repairs & Upgradation of GHS Valpoi, GPMS Valpoi, GPS Valpoi in Sattari Taluka, Goa – Civil, Plumbing & Electrical Works

View Project
Similar Project

Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works-BicholimTaluka-Package E (G.P.M.S. Nanoda, G.P.M.S. Advalpal, G.P.S. Amthane)

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.