Project Duration
Stipulated Date of Commencement
June 25 2018
Stipulated Date of Completion /
Likely Date of Completion July 08 2019
Likely Date of Completion July 08 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,736,901.00
Awarded for
₹ 15,447,215.69
Project highlights
Repairs/Upgradation & maintenance of Government Schools
Contractors
M/s. Arav Infratech Pvt. Ltd.
Consultants
M/s. Creative Abode