Project Duration
Stipulated Date of Commencement
January 31 2005
Stipulated Date of Completion /
Likely Date of Completion July 30 2005
Likely Date of Completion July 30 2005
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,600,000.00
Awarded for
₹ 4,596,000.00
Project highlights
Construction of a building for Government High School consisting of six classrooms and one library, one laboratory, one staff room, toilets for boys and girls
Contractors
M/s. Coastal Builders
Consultants
M/s. Kuvelkar Salkar Associates
See Similar Projects
Repairs/ Upgradation & maintenance of Government schools in the state of Goa – Civil, Plumbing & Electrical works- Package-III (Bicholim Taluka) (Rate Contract)
View Project
Repairs/Upgradation & Maintenance of Govt. Schools in the state of Goa – Package L (Sattari Taluka) – (GPS Barazan, GPS Khadki, GPS Velge, GPS Khotode)
View Project
Repairs /Upgradation & Maintenance of Government schools in the sate of Goa -Civil,Plumbing & Electrical works – Package IV (Sanguem & Dharbandora Taluka)
View Project