Project Duration
Stipulated Date of Commencement
November 09 2018
Stipulated Date of Completion /
Likely Date of Completion March 08 2019
Likely Date of Completion March 08 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 22,119,472.00
Awarded for
₹ 17,220,494.00
Project highlights
Providing furniture and interior works at RMO Hostel at GMC.
Contractors
M/s.Virender Kumar & Co.
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.
See Similar Projects
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Maintenance /Renovation Work of Sub District Hospital at Ponda, Goa – Supply, Installation, Testing and Commissioning of SMF batteries including buyback of old SMF batteries
View Project
Construction of Girls Hostel at Goa Medical College & Hospital at Bambolim, Goa – Interior and Furniture Works
View Project
Major Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa SH : Maintenance Contract for Cold Storages installed in Blood Bank, Microbiology Department and Central Pharmacy in GMC Hospital Complex Bambolim for three years
View Project