Project Duration
Stipulated Date of Commencement December 30 2016
Stipulated Date of Completion /
Likely Date of Completion
May 01 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 134,987,464.00
Awarded for ₹ 147,287,915.08

Project highlights

Construction of Priest Houses, VVIP & VIP Rooms, Centre for Art and Archaeology and Landscaping and External Lighting.

 
Gallery Image
Contractors
M/s. Indage Development Construction Pvt. Ltd.
Gallery Image
Consultants
ABHIJIT SADHALE
 
Similar Projects

See Similar Projects

Similar Project

Repair of the Office Premises of Excise Station,Pernem, Goa – Interior and Furniture Work

View Project
Similar Project

Development Plan of the site of Shree Mahalasa Devi Temple at Verna-Phase I – Civil, Plumbing and Electrical work.

View Project
Similar Project

Design, Supply, Installation and commissioning of seed processing machinery with capcity of 2 tonnes per hour for paddy or 4 tonnes per hour for wheat at Ella, Old Goa.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.