Project Duration
Stipulated Date of Commencement
December 30 2016
Stipulated Date of Completion /
Likely Date of Completion May 01 2018
Likely Date of Completion May 01 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 134,987,464.00
Awarded for
₹ 147,287,915.08
Project highlights
Construction of Priest Houses, VVIP & VIP Rooms, Centre for Art and Archaeology and Landscaping and External Lighting.
Contractors
M/s. Indage Development Construction Pvt. Ltd.
Consultants
ABHIJIT SADHALE