Project Duration
Stipulated Date of Commencement
July 23 2022
Stipulated Date of Completion /
Likely Date of Completion November 22 2023
Likely Date of Completion November 22 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 53,144,732.00
Awarded for
₹ 48,488,436.44
Project highlights
The new building for Directorate of Accounts with a plot area of 5300 sq.m. is a (G+3) Office building with 22 nos. various administrative sections. It also houses a Training hall for 340 pax, Canteen, Bank, ATM and Basement for 75 nos. Car & 45 nos. two wheeler parking.
Contractors
M/s. Mannu Lal & Sons
Consultants
M/s UCJ Architecture & Environment
See Similar Projects
Construction of Forest Headquarters Building at Altinho Old IPHB Complex
View Project
Construction of Forest Headquarters Building at Altinho Old IPHB Complex – Civil,Plumbing, Electrical,HVAC,Lifts and fire fighting works.
View Project
Maintenance of building under DFDA, Bambolim,Goa – SH-Maintenance contract of 180 KVA DG set installed at DFDA, Bambolim for three years.
View Project