Project Duration
Stipulated Date of Commencement
April 26 2007
Stipulated Date of Completion /
Likely Date of Completion October 25 2007
Likely Date of Completion October 25 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,644,386.00
Awarded for
₹ 34,552,373.00
Contractors
M/s. Kirloskar Constructions & Engineers Limited
Consultants
M/s. Construma Consultancy Pvt. Ltd.
Sub Works
This project involved 2 sub works. The details of the same available below
1
Construction of Jetty at Brittona – Additional works.
100% completed
Project Duration
Stipulated Date of Commencement
July 16 2010
Stipulated Date of Completion /
Likely Date of Completion October 15 2010
Likely Date of Completion October 15 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,985,905.00
Awarded for
₹ 2,183,970.00
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Vijaykumar Sawant Associates
2
Construction of Jetty at Brittona – Additional electrical works
100% completed
Project Duration
Stipulated Date of Commencement
April 06 2010
Stipulated Date of Completion /
Likely Date of Completion June 05 2010
Likely Date of Completion June 05 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 609,064.00
Awarded for
₹ 651,172.00
Contractors
M/s. Oman Enterprises
Consultants
In-house (GSIDC)
See Similar Projects
Construction of Bus Stand at Shiroda – Phase II : Civil works, internal electrification and road
View Project
Construction of footpath from Sai Service junction to training college junction at Porvorim – Electrical works
View Project
Widening of road in Calangute – Baga.
View Project





