Project Duration
Stipulated Date of Commencement December 15 2006
Stipulated Date of Completion /
Likely Date of Completion
May 14 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 18,739,000.00
Awarded for ₹ 26,300,000.00

Project highlights

The bridge has an overall length of 150 mts. with a carriage way width of 5.5 mts. The overall length of the approaches is around 300 mts. This bridge serves as an important connectivity to the residents of Ambeshi to proceed to market area like Ponda via Ganjem during monsoon. These people had to walk around 3 kms. through hilly terrain and mining areas to reach market area like Pale thus causing inconvenience especially to school children, ladies etc.

 
Gallery Image
Contractors
M/s. Daftary Descon Engineering Pvt. Ltd.
Gallery Image
Consultants
M/s. Kuvelkar Salkar Associates J/v M/s. Decom Consultant
 
Similar Projects

See Similar Projects

Similar Project

Improvement and Widening to four lane road from km.34/200 to km.35/600 at Navelim including construction of pavement at various places.

View Project
Similar Project

Demolition and Reconstruction of COP Jetty at Panaji

View Project
Similar Project

Bridge connecting Veluz and Dhabos in Valpoi including approaches.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.