Project Duration
Stipulated Date of Commencement July 27 2014
Stipulated Date of Completion /
Likely Date of Completion
December 31 2023
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,550,000,000.00
Awarded for ₹ 4,030,000,000.00

Project highlights

Bridge connecting Panaji and Porvorim of total lenght 5.44 km with cable stayed portion in the river spanning to 620m..

 
Gallery Image
Contractors
M/s. Larsen & Toubro Limited
Gallery Image
Consultants
M/s. TPF Engineering Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Design and construction of Bridge across River Zuari between Amona and Virdi. SH: Supply of LED Fittings, Poles and Brackets

View Project
Similar Project

Demolition of old Existing jetty and Reconstruction of New Fisheries Jetty at Panaji, Goa

View Project
Similar Project

Widening and Improvement of MDR No.2 between chainage 3.40 Km to 9.12 Km from Merces to Goa Velha (Part).

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.