Project Duration
Stipulated Date of Commencement June 20 2008
Stipulated Date of Completion /
Likely Date of Completion
September 20 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ Rs.3,63,53,407.64
Awarded for ₹ 52,100,720.15

Project highlights

Swimming pool (25.40 x 20.40 mts.), with depth varying from 1.098 to 1.824 mts. The size of Baby pool is 5.40 x 5.61 mts. Changing rooms for ladies and gents. Shower rooms for ladies and gents, Office,Common room, adequate toilet facilities, Ample parking facilities, Soft landscaping in the premises with illumination.

 
Gallery Image
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Gallery Image
Consultants
M/s. M. S. Suctancar
 
Similar Projects

See Similar Projects

Similar Project

Construction of Compound Wall for Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.

View Project
Similar Project

Repairs /Upgradation & Maintenance of Government schools in the sate of Goa -Civil,Plumbing & Electrical works – Package IVA (Sanguem Taluka)

View Project
Similar Project

Repairs/Upgradation & maintenance of Government schools in the state of Goa – Civil, Plumbing & Electrical works- Package-IV (Sattari Taluka )

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.