Project Duration
Stipulated Date of Commencement
January 31 2019
Stipulated Date of Completion /
Likely Date of Completion October 09 2019
Likely Date of Completion October 09 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,158,393.21
Awarded for
₹ 11,109,700.15
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s. Anish Associates
Consultants
M/s. Vaishali Pednekar Associates