Project Duration
Stipulated Date of Commencement February 01 2019
Stipulated Date of Completion /
Likely Date of Completion
October 31 2023
Status
100%
Completed
Cost (₹)
Estimated at ₹ 46,281,281.00
Awarded for ₹ 43,882,672.75

Project highlights

Retaining walls,pilling work, embakment, roads,electrical works etc.

 
Gallery Image
Contractors
M/s. Race Constructions
Gallery Image
Consultants
M/s. Keni D’Souza
 
Similar Projects

See Similar Projects

Similar Project

Construction of Bus Stand at Mapusa, Goa – Land Development work (Phase I).

View Project
Similar Project

Improvement and Upgradation of the existing MDR from Dandevaddo to Chandor via Sarzora and Guddi in Cuncolim Constituency.

View Project
Similar Project

Construction and upgradation of fishing jetty at Malim (North Goa) and Cortalim (South Goa).

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.