Project Duration
Stipulated Date of Commencement
November 30 2021
Stipulated Date of Completion /
Likely Date of Completion December 29 2023
Likely Date of Completion December 29 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,217,212.50
Awarded for
₹ 2,438,624.00
Project highlights
Landscaping works
Contractors
M/s.Limboo Softscape
Consultants
M/s. Pankaj Joshi Consultants