Project Duration
Stipulated Date of Commencement
January 15 2015
Stipulated Date of Completion /
Likely Date of Completion July 14 2015
Likely Date of Completion July 14 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ Rs. 2,38,59,753.00
Awarded for
₹ 27,299,749.39
Project highlights
Construction of 10 cattle sheds
Contractors
M/s. Bharti Infrastructure Developers
Consultants
M/s. Creative Abode