Project Duration
Stipulated Date of Commencement
September 26 2019
Stipulated Date of Completion /
Likely Date of Completion February 29 2024
Likely Date of Completion February 29 2024
Status
100%
Completed
Cost (₹)
Estimated at
₹ 31,074,285.00
Awarded for
₹ 27,291,564.00
Project highlights
The scope of work includes false ceiling, paritions, panelling, granite cladding, tac tiles, signages, aluminium louvers, etc.
Contractors
M/s. Virender Kumar & Co.
Consultants
M/s. M:OFA Studios Pvt. Ltd.