Project Duration
Stipulated Date of Commencement December 11 2021
Stipulated Date of Completion /
Likely Date of Completion
August 10 2022
Status
100%
Completed
Cost (₹)
Estimated at ₹ 8,57,02,662.81
Awarded for ₹ 8,86,24,433.05

Project highlights

Construction of 40m four lane brisge across river Tar at Mapusa

 
Gallery Image
Contractors
M/s. PRN Infratech
Gallery Image
Consultants
M/s.Madhav Kamat & Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of Bridge at Gaundali including approaches.

View Project
Similar Project

Construction Of new bypass road from Ambeudak Sanvordem to Devnamol in V.P. Kallem including drainage.

View Project
Similar Project

Providing and applying high build, crack building, electromeric, protective and waterproof coating to the Grade separator (2 flyovers) at Dabolim airport.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.