Project Duration
Stipulated Date of Commencement
April 04 2015
Stipulated Date of Completion /
Likely Date of Completion July 03 2016
Likely Date of Completion July 03 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 93,194,540.00
Awarded for
₹ 117,089,723.00
Project highlights
Market Complex, Library, Panchayat Ghar, Gymnasium, Anganwadi, Multipurpose Hall,etc.
Contractors
M/s. Kalyani Global Engineering Pvt. Ltd.
Consultants
M/s. Vijaykumar Sawant Associates