Project Duration
Stipulated Date of Commencement
August 28 2006
Stipulated Date of Completion /
Likely Date of Completion May 27 2007
Likely Date of Completion May 27 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 41,708,331.00
Awarded for
₹ 48,000,000.00
Contractors
M/s. Standard Constructions
Consultants
M/s. Effective Architectural Services