Project Duration
Stipulated Date of Commencement
January 21 2019
Stipulated Date of Completion /
Likely Date of Completion April 20 2019
Likely Date of Completion April 20 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,283,986.50
Awarded for
₹ 7,900,444.46
Project highlights
Power supply for High Court Complex
Contractors
M/s. Consistent Engineers
Consultants
–
See Similar Projects