Project Duration
Stipulated Date of Commencement
May 23 2013
Stipulated Date of Completion /
Likely Date of Completion August 22 2013
Likely Date of Completion August 22 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,265,380.00
Awarded for
₹ 7,015,854.00
Project highlights
School Building with 4 classrooms of international size 60 sq. m
Contractors
M/s. H. Candolkar & Sons
Consultants
M/s. Datta Kare Associates