Project Duration
Stipulated Date of Commencement
October 29 2019
Stipulated Date of Completion /
Likely Date of Completion August 31 2023
Likely Date of Completion August 31 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,590,969.80
Awarded for
₹ 15,525,496.81
Project highlights
Repair and Upgradation Works of school
Contractors
M/s. Sunil Enterprises
Consultants
M/s. Mahimtura Consultants Pvt Ltd