Project Duration
Stipulated Date of Commencement
December 17 2012
Stipulated Date of Completion /
Likely Date of Completion February 16 2013
Likely Date of Completion February 16 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,590,641.00
Awarded for
₹ 5,590,300.00
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Effective Architectural Services