Project Duration
Stipulated Date of Commencement
November 06 2008
Stipulated Date of Completion /
Likely Date of Completion January 05 2009
Likely Date of Completion January 05 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 43,00,000.00
Awarded for
₹ 38,00,000.00
Contractors
M/s. Siemens Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.