Project Duration
Stipulated Date of Commencement
January 17 2013
Stipulated Date of Completion /
Likely Date of Completion February 15 2013
Likely Date of Completion February 15 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,02,563.00
Awarded for
₹ 2,983,810.00
Project highlights
Landscaping works
Contractors
M/s. Vrindavan Agricultural Services
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.