Project Duration
Stipulated Date of Commencement February 15 2014
Stipulated Date of Completion /
Likely Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at ₹ 35,090,528.00
Awarded for ₹ 33,945,797.37

Project highlights

Providing interior furniture, false ceiling, parttions and other furnishings

 
Gallery Image
Contractors
M/s. T. S. Mistry,
Gallery Image
Consultants
M/s KICONS
 
Similar Projects

See Similar Projects

Similar Project

Construction of Toilet Block at Chapora

View Project
Similar Project

Construction of building at Patto with provision for Gas insulated substation Panaji Phase I

View Project
Similar Project

Civil, Plumbing & internal electrical works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.