Project Duration
Stipulated Date of Commencement
January 23 2015
Stipulated Date of Completion /
Likely Date of Completion May 22 2015
Likely Date of Completion May 22 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,853,393.00
Awarded for
₹ 13,328,661.00
Project highlights
Additional furniture & minor civil works.
Contractors
M/s. Concept Creators
Consultants
M/s. Nitin Arolkar