Project Duration
Stipulated Date of Commencement
October 20 2017
Stipulated Date of Completion /
Likely Date of Completion October 19 2018
Likely Date of Completion October 19 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 37,514,162.39
Awarded for
₹ 36,984,361.28
Project highlights
The work includes construction of front side compound wall of approx. 2040 m length for GMC complex.
Contractors
M/s. R. V. Construction
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd,Inhouse,