Project Duration
Stipulated Date of Commencement November 05 2014
Stipulated Date of Completion /
Likely Date of Completion
May 04 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 292,919,099.00
Awarded for ₹ 357,020,022.60

Project highlights

New building for the CHC with 80 bed capacity

 
Gallery Image
Contractors
M/s. MVR Infra Projects Pvt. Ltd
Gallery Image
Consultants
M/s. Saolapurkar and Associates
 
Similar Projects

See Similar Projects

Similar Project

Demolition and reconstruction of 220 bedded hospital in place of Public Health Center – (I. D. Hospital) at Sadar Ponda Goa.

View Project
Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in South Goa – S.H- Maintenance /Renovation work of Community Health Center at Canacona – Maintenance Contract for Schindler Elevator installed at Canacona CHC

View Project
Similar Project

Upgradation of Hospital facilities at Goa Medical College, Bambolim, Hospicio Hospital at Margao and RMD at Thane & Keri. SH- Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa-Extension of Ward 125 for Cardiology Department at Goa Medical College, Bambolim-Goa.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.