Project Duration
Stipulated Date of Commencement
December 24 2009
Stipulated Date of Completion /
Likely Date of Completion February 23 2011
Likely Date of Completion February 23 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 90,55,820.00
Awarded for
₹ 88,37,468.40
Project highlights
Rural medical dispensary is provided with Pathology room, Ultra sound, Dentists room, Pediatric room, Pharmacy, Gynac room, 2 bed ward, Doctors room, reception/waiting area and adequate toilet facilities
Contractors
M/s. M. B. Kinlekar
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd