Project Duration
Stipulated Date of Commencement
January 05 2022
Stipulated Date of Completion /
Likely Date of Completion February 04 2022
Likely Date of Completion February 04 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,899,896.00
Awarded for
₹ 1,880,600.20
Project highlights
Erection of 11KV line from Electricity Department feeder to bus stand substation.
Contractors
M/s. Volton Engineering (I) Pvt. Ltd.,
Consultants
M/s UCJ Architecture & Environment