Project Duration
Stipulated Date of Commencement
January 14 2013
Stipulated Date of Completion /
Likely Date of Completion May 13 2013
Likely Date of Completion May 13 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,848,415.93
Awarded for
₹ 4,426,921.55
Project highlights
External Electrical Work
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
Consultants
M/s. Rahul Deshpande & Associates
See Similar Projects
Dismantling of HT overhead lines and supplying & laying of HT Underground cables at Panjim – HT Cable work from EDC Substation to Chimbel junction – Additional Work
View Project
Improvement and Upgradation of road network at Piligao, Curti, Ponda Town and Chodan.
View Project
St. Inez Creek Barricading
View Project





