Project Duration
Stipulated Date of Commencement
July 30 2008
Stipulated Date of Completion /
Likely Date of Completion October 29 2009
Likely Date of Completion October 29 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 41,612,031.00
Awarded for
₹ 80,505,716.00
Project highlights
Construction of bridge on Khandepar river at Codli – Dhabal, Goa.
Contractors
M/s. Daftary Descon Engineering Pvt. Ltd.
Consultants
M/s. Mahimtura Consultants Pvt. Ltd.