Project Duration
Stipulated Date of Commencement November 01 2004
Stipulated Date of Completion /
Likely Date of Completion
April 30 2005
Status
100%
Completed
Cost (₹)
Estimated at ₹ 17,434,621.00
Awarded for ₹ 17,783,313.00

Project highlights

• Length : 52 m.
• Three continuous spans with cast-in-situ R.C.C. T-beam superstructure.
• Carriageway 7.5 m wide with kerbs, railings and footpaths on both the sides.
• Approaches on Margao and Colva side.
• Electric poles with fixtures on the bridge and approaches.

 
Gallery Image
Contractors
M/s. Naik Constructions
Gallery Image
Consultants
M/s. M. V. S. Borcar & Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of bridge over river Zuari at St. Jacinto Island in Village Panchayat of Chicalim

View Project
Similar Project

Construction of Concrete Pavement Road and other development work from Miramar Circle to NIO Circle and Raj Bhavan

View Project
Similar Project

Construction over bridge at Valvanti river connecting Bhandarwada to Vithalapur Sankhali.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.