Project Duration
Stipulated Date of Commencement
December 11 2018
Stipulated Date of Completion /
Likely Date of Completion December 20 2019
Likely Date of Completion December 20 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 233,805,559.34
Awarded for
₹ 249,915,774.13
Project highlights
1.To develop and beautify both sides of the existing road at Khareabandh area.
2.Construction of Footpath from the front of theSt. Micheal Church towards the main MDR road at Orlim.
3.Construction of retaining wall with illumination and beautification of road with the Foot Path along the road at Varca, Benaulim, Seraulim & Cavelossim.
Contractors
M/s.Souza Engineers Contractors Pvt. Ltd.
Consultants
M/s. Construma Consultancy Pvt. Ltd.
See Similar Projects
Construction of Pedestrian Arch Bridge connecting Mandovi River Promenade and DB Road, over St. Inez Creek near ESG Building at Panaji
View Project
Design & Construction of Bridge across river Zuari between Amona and Virdi.
View Project
Improvement / Hot mixing of roads in Arpora – Candolim.
View Project