Project Duration
Stipulated Date of Commencement
June 27 2008
Stipulated Date of Completion /
Likely Date of Completion September 26 2008
Likely Date of Completion September 26 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,370,852.00
Awarded for
₹ 15,401,378.00
Contractors
M/s. Royal Safe Company
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd