Project Duration
Stipulated Date of Commencement
June 16 2006
Stipulated Date of Completion /
Likely Date of Completion April 15 2007
Likely Date of Completion April 15 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 45,331,777.00
Awarded for
₹ 43,374,376.00
Project highlights
Power upgradation work includes utility buiding, 33 KV substation, HT panels, LT panels and 11 KV ring main unit (RMU) and cabling.
Contractors
M/s. ABB Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
See Similar Projects
Supply, installation, testing, commissioning of fire detection and alarm system
View Project
Landscaping works
View Project
Supply, Installation and Testing and Commissioning of Blood warmer
View Project





