Project Duration
Stipulated Date of Commencement
January 29 2021
Stipulated Date of Completion /
Likely Date of Completion September 28 2021
Likely Date of Completion September 28 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,193,470.00
Awarded for
₹ 39,593,350.00
Project highlights
Deep clenaing and housekeeping services for new High Court Building
Contractors
M/s. Ecoclean System and solutions
Consultants
M/s LKS India Pvt. Ltd.