Project Duration
Stipulated Date of Commencement
December 08 2009
Stipulated Date of Completion /
Likely Date of Completion December 27 2009
Likely Date of Completion December 27 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 747,730.00
Awarded for
₹ 883,200.00