Project Duration
Stipulated Date of Completion /
Likely Date of Completion November 25 2009
Likely Date of Completion November 25 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 545,983.00
Awarded for
₹ 542,098.34
Project highlights
1 no. Server, 1 no. Red Hat Linux Enterprise Advanced Server Edition ver 5.0 Software, Ethernet Switches and Patch Cords
Contractors
M/s. Smart Information Systems
Consultants
In-house (GSIDC)