Project Duration
Stipulated Date of Commencement December 28 2023
Stipulated Date of Completion /
Likely Date of Completion
August 31 2024
Status
28%
Completed
Cost (₹)
Estimated at ₹ 21,307,622.00
Awarded for ₹ 22,871,315.00

Project highlights

Project includes development of work place at third floor, such as – interior and other allied works

 
Gallery Image
Contractors
M/s. Concept Creator
Gallery Image
Consultants
M/s. UCJ Architecture & Environment
 
Similar Projects

See Similar Projects

Similar Project

Improving & Revamping of Water supply, Power supply & Sewerage Netwoirk at Goa Medical College & Hospital, Bambolim-Goa – Phase II – SH – Revamping of Existing Fire fighting Grid at GMC, Bambolim-Goa.

View Project
Similar Project

Construction of Office of Inspectorate of Factories & Boilers at Altinho, Panaji-Goa.

View Project
Similar Project

Construction of New Hostel Block for Institute of Psychiatry & Human Behaviour

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.