Project Duration
Stipulated Date of Commencement June 24 2022
Stipulated Date of Completion /
Likely Date of Completion
September 30 2024
Status
34.1%
Completed
Cost (₹)
Estimated at ₹ 256,977,576.16
Awarded for ₹ 263,203,536.94

Project highlights

New Hostel Block is proposed in IPHB Campus for Resident Doctors and New students to be inducted for the courses in IPHB

 
Gallery Image
Contractors
M/s. S K Construction
Gallery Image
Consultants
M/s. FP Project Management
 
Similar Projects

See Similar Projects

Similar Project

Providing interiors, electrifications and other amenities to the office premises of Commercial Tax Department situated at Mapusa.

View Project
Similar Project

Construction of New District & Session Court Complex at Merces,Tiswadi,Goa -Civil,Plumbing,Electrical, Lifts, HVAC,fire fighting and other allied works.

View Project
Similar Project

Maintenance works at Goa Medical College and Hospital S.H.: Maintenance Contract for the OTIS make 15 passenger cum bed lift installed at TB and Chest Diseases Hospital, St. Inez Goa for a period of three years (2020-2023).

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.