Project Duration
Stipulated Date of Commencement
July 23 2022
Stipulated Date of Completion /
Likely Date of Completion November 22 2023
Likely Date of Completion November 22 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 53,144,732.00
Awarded for
₹ 48,488,436.44
Project highlights
The new building for Directorate of Accounts with a plot area of 5300 sq.m. is a (G+3) Office building with 22 nos. various administrative sections. It also houses a Training hall for 340 pax, Canteen, Bank, ATM and Basement for 75 nos. Car & 45 nos. two wheeler parking.
Contractors
M/s. Mannu Lal & Sons
Consultants
M/s UCJ Architecture & Environment
See Similar Projects
Supply, Installation, Testing & Commissioning of CCTV system at Goa Medical College.
View Project
Supply and laying of 33KV HT cable from Sai service junction to the new High Court Complex and allied electrical works
View Project
Construction of New High Court Complex at Penha De France, Porvorim, Goa- S.H: Laying of water supply pipeline for permanent connection
View Project