Project Duration
Stipulated Date of Commencement
March 26 2022
Stipulated Date of Completion /
Likely Date of Completion June 25 2022
Likely Date of Completion June 25 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,386,939.00
Awarded for
₹ 7,200,000.00
Project highlights
Design, Supply, Installation and Commissioning of Seed Processing Machinery with capacity of 2 Tonnes per hour for Paddy OR 4 Tonnes per hour for Wheat.